Performance Statistics

Lead time, aging, throughput Β· extracted 2026-06-18

Total
218
Pending
131
Completed
75
Verified
62
Completion %
34.4%
Verification %
28.4%
ID β†’ Completion
10.1
days avg
8
median
Based on 75 resolved items
ID β†’ Verification
13.6
days avg
11.5
median
Based on 62 verified items
ID β†’ Last Update
8.5
days avg
7.0
median
First action proxy Β· 218 items
Completion β†’ Verification
4.1
days avg
3.0
median
Verification lag Β· 62 items

Pending items β€” age distribution

Days since identified, for 131 open items

Completions per week

Last 12 weeks (Date Completed)

Avg lead time by Type

Days ID β†’ Completion (resolved items only)

Completion rate by Type

% of items in Complete/Verified/Out-of-scope-Confirmed

Lead time by Creator

Avg days from identification to completion (resolved items only)

Creator Avg days (ID→Complete) Items resolved Speed indicator
Amazon / SAT 30 5
Slow
Amazon / WHS Safety 20 2
Normal
Amazon / ATP Adhoc 8.4 68
Fast

🐒 Slow movers β€” oldest Pending

Top 10 open items by age (days since identified)

Punchlist ID Age (days) Type Finding Creator
EMA5-2026-421122440 58 Electrical Scale Technician Checklist sign off Amazon / SAT
EMA5-2026-42112120 58 Software Unable to test Upstream/Downstream Amazon / SAT
EMA5-2026-421122252 58 Software Bizerba scale faults Amazon / SAT
EMA5-2026-51132945 48 Safety Electrical PID Isolators are behind fence lines Amazon / SAT
EMA5-2026-5795544 42 Software F406 8001 estop location on scada Amazon / ATP Adhoc
EMA5-2026-512115011 37 SCADA E-stop manual line on 406 is not well positioned on SCADA Amazon / ATP Adhoc
EMA5-2026-513161014 36 Asset Tag Tag number on PLC406 mismatch Amazon / ATP Adhoc
EMA5-2026-513155913 36 SCADA E-stop not lighting up in red on SCADA when pressed Amazon / ATP Adhoc
EMA5-2026-513154423 36 SCADA PLC406 device disabled alarm number mismatch Amazon / ATP Adhoc
EMA5-2026-513154041 36 SCADA Alarm message number does not match jam sensor number PLC406 Amazon / ATP Adhoc

🧠 Key Insights

Automated observations based on current data

πŸ’‘
Acceptable first response
TGW takes on average 8.5 days to first action. Acceptable, but there is room to tighten up, especially as handover approaches.
βœ…
Lead time manageable
Average resolution time (10.1 days) is well below the handover deadline (50 days remaining). Current pace is sustainable.
⚠️
11 items pending >30 days
11 open punchlists have been unresolved for over 30 days. The oldest is 58 days old (ID: EMA5-2026-421122440). These are at risk of missing the handover date.
βœ…
Efficient verification pipeline
Amazon verifies completed items in 4.1 days on average β€” a tight and efficient loop.
πŸ’‘
Backlog projection
At the current pace of ~14 completions/week (4-week avg), clearing the 131 pending items would take ~9 weeks β€” beyond the handover window.
⚠️
5 items in Verification Fail
5 items were rejected by Amazon verification. These require rework and re-verification β€” double cost in time.
βœ…
Safety Mechanical resolves fastest
"Safety Mechanical" items close in 7 days on average, vs 30 days for "Software". Focus additional capacity where lead times are longest.
⚠️
More than half still open
Only 34.4% of punchlists are completed and 28.4% fully verified. With 50 days to handover, this represents a significant outstanding workload.